Posted on June 21, 2024
Categories: Active Projects, Elementary

4600 W. Girard Avenue, 19131 | Grades: K-8

Active Project (s):

Exterior Structural Renovations

  • Budget: $4,645,466
  • BOE Approval Date: TBD
  • Status: Pending Bid Process

Past Projects

Modernization of specified classrooms and installation of new furnishings and technology. Modernization of classrooms to include replacement of movable partitions with infill walls; Wall and ceiling repainting; Ceiling and door replacement; New casework, cubbies, and built-in shelving; Refurbished and new classroom teaching boards.; Install new lighting, clocks, power, data receptacles, and conduit pathways;  Classroom sink and toilet replacement; Heating valve and trap replacement; Hydration Station replacement; New window AC units; VCT floor replacement and Hardwood floor refinishing; All new classroom furnishings and new interactive Panelboards; Slate chalkboards and cork bulletin boards will be replaced with magnetic white marker boards and tack boards.

  • Budget: $ 797,000
  • BOE Approval  4/22/21

Modernization of specified classrooms and installation of new furnishings and technology. Modernization of classrooms to include replacement of movable partitions with infill walls; Wall and ceiling repainting; Ceiling and door replacement; New casework, cubbies, and built-in shelving; Refurbished and new classroom teaching boards.; Install new lighting, clocks, power, data receptacles, and conduit pathways;  Classroom sink and toilet replacement; Heating valve and trap replacement; Hydration Station replacement; New window AC units; VCT floor replacement and Hardwood floor refinishing; All new classroom furnishings and new interactive Panelboards; Slate chalkboards and cork bulletin boards will be replaced with magnetic white marker boards and tack boards.

  • Budget: $ 93,794
  • BOE Approval: 4/22/21

Modernization of specified classrooms and installation of new furnishings and technology. Modernization of classrooms to include replacement of movable partitions with infill walls; Wall and ceiling repainting; Ceiling and door replacement; New casework, cubbies, and built-in shelving; Refurbished and new classroom teaching boards.; Install new lighting, clocks, power, data receptacles, and conduit pathways;  Classroom sink and toilet replacement; Heating valve and trap replacement; Hydration Station replacement; New window AC units; VCT floor replacement and Hardwood floor refinishing; All new classroom furnishings and new interactive Panelboards; Slate chalkboards and cork bulletin boards will be replaced with magnetic white marker boards and tack boards.

  • Budget: $345,144
  • BOE Approval: 4/22/21

New Cafeteria to include the complete demolition and reconstruction of the cafeteria, including kitchen cooling, HVAC, and lighting.
Budget: $1,771,383

  • BOE Approval Date: May 24, 2021
  • Completed: August 2022