3301 Old York Rd, 19140 | Grades: PreK-8
Active Projects
Major Renovations (Phase III):
- Refinish all classrooms, corridors, and ancillary spaces; Upgrade IT; Create accessible toilet rooms; Upgrade electrical service and distribution; Replace all roofs; Replace all windows; Refurbish exterior masonry
- Budget: $11,001,648
- Status: Pending Bid Process
TPL Playground Improvement
- Budget: $969,510
- BOE Approval Date: TBD
- Status: Design Phase
The GESA program will focus on the following Energy Conservation Measures (ECMs): LED light fixtures and controls: Installation of high-efficiency LED lighting fixtures to both the interior and exterior; Automatic Temperature Controls (ATC) upgrades and repairs to allow improved comfort; levels and reduce energy consumption.; New boilers and chillers to improve cooling and new terminal units for heating and ventilation.; Steam to hot water heating conversions; New Air Handling Units (AHUs) for improved heating and ventilation.; Electrical System upgrades as needed; seal the envelope of buildings to reduce heat loss
- Budget: $4,487,387
- Board Approval Date: May 27, 2022
- Status: Construction Phase