Science Lab Renovations at Penn Treaty
Design Project Manager: Gamil Hall
Construction Project Manager: Frank Ratka
Project Inspector: Matt McLaughlin
Design Firm: Vitteta
General Contractor: Bedwell
Mechanical Contractor: E.J. Meloney Inc.
Electrical Contractor: Madden Electrical
Plumbing Contractor: Five Star
![Penn Treaty Science Lab Room 404 Wall Demo - Matthew McLaughlin](https://www.philasd.org/capitalprograms/wp-content/uploads/sites/18/2021/02/Penn-Treaty-Science-Lab-Room-404-Wall-Demo-Matthew-McLaughlin-225x300.jpg)
![Penn Treaty Science Lab Room 406 Framing - Matthew McLaughlin](https://www.philasd.org/capitalprograms/wp-content/uploads/sites/18/2021/02/Penn-Treaty-Science-Lab-Room-406-Framing-Matthew-McLaughlin-225x300.jpg)
![Penn Treaty Science Lab Room 306 Plaster Ceiling Demo - Matthew McLaughlin](https://www.philasd.org/capitalprograms/wp-content/uploads/sites/18/2021/02/Penn-Treaty-Science-Lab-Room-306-Plaster-Ceiling-Demo-Matthew-McLaughlin-225x300.jpg)
DECEMBER 1, 2020
Project Start
181 DAYS
Project Duration
MAY 31, 2021
Project Completion
$1,200,000
Construction Budget
Environmental Results
1/18/21 – TEM Asbestos Analysis