Posted on June 28, 2024
Categories: Active Projects, Elementary

1501 West Diamond Street, 19121 | Grades: K-8

Active Project(s):

Phase two of schoolyard improvement; basketball and tennis court to be rebuilt and new fencing and seating areas installed.

  • Budget: $ 675,000
  • BOE Approval:
  • Status:

Past Projects

Flood Remediation

  • General Contract Budget: $874,000
  • Mechanical Contract Budget: $1,217,760
  • Plumbing Contract Budget: $427,500
  • Electrical Contract Budget: $1,588,880
  • BOE Approval date: 5/28/20
  • Scope of Work: Phase 1 of schoolyard improvement consisting of flood remediation